Project Description

Structural building modification

This warehouse needed additional space for a refrigerated storage solution, so we supplied the structural steel for the project.

Project Info:

  • GROSS FLOOR AREA: 1000 SQ. FT
  • STRUCTURE WEIGHT: 10,000 LB STEEL
  • PROJECT VALUE: $80.000
  • LOCATION: FLINT ROAD, TORONTO
  • FABRICATION 1 WEEK. ERECTION 1/2 WEEK
  • EQUIPMENT SUPPLIER: HERC RENTALS
  • JLG 340AJĀ  + GENIE Z-34/22 + JLG 1255
  • ENGINEER: VVCEM INC.
  • CWB INSPECTION: ACE TAKE GROUP
  • DECK SUPPLIER: CAN AM P3606 22 GA. G90